Summary
Two significant construction developments occurred over the long
weekend and since our last Construction Law Update. First, limitation
periods and procedural time periods under the Construction
Act that were suspended as of March 16, 2020, will be
reinstated as of April 16, 2020. Second, the list of
"essential" construction projects was expanded to include
projects due to be completed before October 4, 2020 and that would
provide additional capacity in the production, processing,
manufacturing or distribution of food, beverages or agricultural
products.
Limitation Periods and Procedural Time Periods
As stated in our last Construction Law Update, the Ontario
government suspended limitation periods and procedural time periods
in Ontario proceedings as part of its emergency orders made under
the Emergency Management and Civil Protection Act (the
"Suspension Order"). We noted the
Suspension Order likely suspended, as of March 16, 2020, the
deadlines for preserving and perfecting liens and releasing
statutory holdback, which had the potential to impact the flow of
funds through the construction pyramid. We also noted certain trade
and legal associations were seeking direction from the Ontario
government regarding the effect of this suspension on construction
projects, including whether modifications needed to be made to
allow timelines under the Construction Act to be
reinstated.
The Ontario government considered the construction industry's
concerns, and amended the Suspension Order to provide that, from
April 16, 2020, the suspensions do not apply to provisions of the
Construction Act. The actual order has not been made publically
available, but is expected to be posted shortly to the Regulations
under the Emergency Management and Civil Protection Act here.
The result is that deadlines under the Construction Act,
including for preserving and perfecting liens (and, thus, releasing
statutory holdback), will be reinstated, but will have been
suspended for the 31-day period of March 16, 2020 to April 16,
2020.
A similar order was made in British Columbia on
Friday, exempting the Builders Lien Act from British
Columbia's emergency order suspending "every mandatory
limitation period and any other mandatory time period that is
established in an enactment or law of British Columbia within which
a civil or family action, proceeding, claim or appeal must be
commenced". The BC suspension of the Builders Lien
Act time periods runs from March 26, 2020 to April 15,
2020.
Expansion of Essential Construction Projects
As noted in our last Construction Law Update, although the majority
of construction projects were initially classified as
"essential" businesses, the list was later significantly
reduced. However, on April 9, 2020, the list was expanded by deeming essential
"construction projects that are due to be completed before
October 4, 2020 and that would provide additional capacity in the
production, processing, manufacturing or distribution of food,
beverages or agricultural products."
The list of construction projects now deemed to be essential
businesses and allowed to remain open are:
- Construction projects and services associated with the healthcare sector, including new facilities, expansions, renovations and conversion of spaces that could be repurposed for health care space.
- Construction projects and services required to ensure safe and reliable operations of, or to provide new capacity in, critical provincial infrastructure, including transit, transportation, energy and justice sectors beyond the day-to-day maintenance.
- Critical industrial construction activities required for:
- the maintenance and operations of petrochemical plants and refineries;
- significant industrial petrochemical projects where preliminary work has already commenced; or
- industrial construction and modifications to existing industrial structures limited solely to work necessary for the production, maintenance, and/or enhancement of Personal Protective Equipment, medical devices (such as ventilators), and other identified products directly related to combatting the COVID-19 pandemic.
- Construction projects that are due to be completed before October 4, 2020 and that would provide additional capacity in the production, processing, manufacturing or distribution of food, beverages or agricultural products.
- Residential construction projects where:
- a footing permit has been granted for single family, semi-detached and townhomes;
- an above grade structural permit has been granted for condominiums, mixed use and other buildings; or
- the project involves renovations to residential properties and construction work was started before April 4, 2020.
- Construction and maintenance activities necessary to temporarily close construction sites that have paused or are not active and to ensure ongoing public safety.
For the requirements that must be met on continuing construction
projects, as well as activities that can continue at construction
projects not deemed essential, please see our previous Construction Law Update.
Goodmans will continue to monitor developments, and will provide
further updates as information becomes known. To discuss these
developments, or other ways in which COVID-19 may affect your
construction project, please contact any member of our
Construction and Infrastructure Group.
The content of this article is intended to provide a general guide to the subject matter. Specialist advice should be sought about your specific circumstances.