On 29 May 2020, the New South Wales Court of Appeal (Court of Appeal) handed down its decision in C&V Engineering Pty Ltd v Hamilton & Marino Builders Pty Ltd [2020] NSWCA 103. The case deals with a common dispute in construction supply contracts: whether the contract is a 'schedule of rates contract' or a 'lump sum contract'.

Facts

Hamilton & Marino Builders Pty Ltd (Builder) was engaged to construct a 55-unit development which required the supply and installation of 'plates' and 'angles'.

The Builder requested C&V Engineering Pty Ltd (Supplier) to provide a quote for the plates and angles. At the time, the actual number of plates and angles required for the development was uncertain and the Supplier provided a quote for the supply and installation of 1,000 plates and angles, (arguably) a lump sum contract.

The Builder notified the Supplier that substantially lesser plates and angles were required for the development. The Supplier refused to perform further work on the basis that the Builder had breached the contract between the parties.

The Supplier then commenced proceedings in the District Court of New South Wales (District Court) against the Builder to recover the balance on a lump sum contract. In response, the Builder argued it had only agreed to the price quoted by the Supplier for the supply and installation of angles and plates per piece, and not for a fixed quantity.

The District Court decision

In the District Court, the primary judge found for the Builder. The Supplier appealed the decision on the basis that the primary judge's construction of the contract as not being for a fixed volume of plates and angles, was incorrect.

The Court of Appeal decision

The Court of Appeal unanimously dismissed the appeal. It found that upon the proper construction of the email exchanges between the Builder and Supplier:

  • the contract was not for a fixed volume of plates and angles;
  • it was an objective fact that neither party knew how many plates and angles would be required at the time of contracting; and
  • the Builder 'accepted' the rates in the quote to be applied to the plates and angles "as required".

Concluding Remarks

The key takeaways from this case are:

  • during contract formation, parties need to clearly decide on whether the contract is based on a schedule of rates or is a lump sum contract;
  • avoid the use of multiple contractual documents; and
  • consolidate the parties' intentions into one final contractual document to avoid confusion.

Vincent Young provided practical and commercial advice to the Builder during the life of the dispute and convinced the District Court and the Court of Appeal that a schedule of rates contract was, in fact, the correct contract in this dispute. Vincent Young can assist you too.

Co-authored by Robert Chen

The content of this article is intended to provide a general guide to the subject matter. Specialist advice should be sought about your specific circumstances.