United States: Ohio Enacts Sweeping Energy Legislation: HB 6 Bails Out Nuclear, Coal; Rolls Back Renewables And Energy Efficiency

Opponents Pursue Referendum

On July 23, 2019, Ohio Governor Mike DeWine (R) signed House Bill 6 (HB 6) into law. As detailed below, HB 6:

  1. Adds new ratepayer charges for a $150 million per year "Nuclear Generation Fund" and a $20 million per year "Renewable Generation Fund" to provide subsidies for two nuclear and six permitted, utility-scale solar projects in Ohio from 2021 through 2027;
  2. Significantly reduces Ohio's renewable portfolio standard (RPS) and terminates the RPS at the end of 2026;
  3. Ends Ohio's annual energy efficiency savings requirements on December 31, 2020 while reducing the total cumulative savings requirement to a collective benchmark of 17.5%, a target that the four Ohio utilities are likely to meet primarily or entirely through existing savings; and
  4. Allows the Ohio distribution utility owners of the Ohio Valley Electric Corporation (OVEC) – AEP Ohio, Duke Energy Ohio, and Dayton Power & Light – to recover the net costs of OVEC's coal plants in Ohio and Indiana from Ohio utility ratepayers through 2030.

HB 6 is scheduled to take effect after October 21, 2019 – 90 days from Governor DeWine's signature. However, a group called "Ohioans Against Corporate Bailouts" (OACB) has begun the process of placing a referendum on the November 2020 ballot to repeal the law. OACB took the initial required steps of submitting at least 1,000 signatures along with a summary of the proposed referendum to the Attorney General, and after revising and resubmitting the summary it was approved as of August 30, 2019, as "fair and truthful" with the necessary valid signatures as required by law. The petitioners must now submit 265,774 signatures of registered Ohio voters (from at least 44 of the 88 Ohio counties, with at least 3 percent of total voters from each of those counties) by October 21, 2019, to place the referendum on the November 2020 ballot. If OACB meets these requirements, HB 6 is stayed until Election Day 2020.

1. Nuclear and Renewable Generation Funds (R.C. 3706.40-3706.65)

  1. The Ohio Air Quality Development Authority (OAQDA) will distribute $150 million per year to approved owners/ operators of qualifying nuclear resources and $20 million per year to approved owners/operators of qualifying renewable resources at a rate of $9/MWh.

    1. A "qualifying nuclear resource" must be located in Ohio and fueled by nuclear power (R.C. 3706.40(A)).
    2. A "qualifying renewable resource" must use solar as the primary energy source, have obtained a certificate for construction of a major utility facility from the Ohio Power Siting Board before June 1, 2019, and be interconnected with PJM1 (R.C. 3706.40(B)).
    3. An application from a "qualifying nuclear resource" or "qualifying renewable resource" must be submitted to the OAQDA by February 1, 2020. An applying nuclear resource must provide specified financial data and projections along with any other information that demonstrates that the resource is projected not to continue being operational (R.C. 3706.41).
    4. The OAQDA must approve an application by March 31, 2020, if the resource meets the definition of a qualifying nuclear or renewable resource, and for a nuclear resource if its application meets the requirements under R.C. 3706.41 and it maintains a principal place of business and a substantial presence in Ohio (R.C. 3706.43).
    5. Approved nuclear or renewable resources must report their MWh generation by quarter to OAQDA starting by April 7, 2020. OAQDA will issue a credit for every MWh reported and approved at a rate of $9 per generation credit for each resource (R.C. 3706.45).
    6. Distribution of funds will occur quarterly from April 2021 through January 2028, for credits approved for the quarter 12 months prior (R.C. 3706.55). The methodology for dealing with shortfalls in the nuclear or renewable funds is addressed by R.C. 3706.59.
    7. The Public Utilities Commission of Ohio (PUCO) must conduct a management and financial review of a qualifying nuclear resource receiving credits under R.C. 3706.55, and its owner or operator, by May 1 of each year for 2021 through 2027 (R.C. 3706.61). The PUCO shall submit a report summarizing the findings of each annual audit to the Senate President, House Speaker, and OAQDA. The report will be public, excluding confidential or proprietary information. The OAQDA may reduce or cease payments if:

      1. The Federal Energy Regulatory Commission or Nuclear Regulatory Commission has established an incentive to continue the resource's commercial operation;
      2. The resource is no longer a qualifying nuclear resource (i.e., the owner/operator can no longer demonstrate that the resource is projected not to continue being operational) or no longer has a principal place of business and substantial presence in state;
      3. The resource has applied to decommission before May 1, 2027; or
      4. The market price for energy is above a "strike price" of $46/MWh.
  2. The PUCO must determine the amounts to be collected from each Ohio electric distribution utility for the nuclear and renewable generation funds, and the charges for each of their customers to be effective by January 1, 2021, subject to limits on monthly charges per customer as follows (R.C. 3706.46):

    1. Residential customers: 85 cents
    2. Self-assessing industrial customers under R.C. 5727.81 (using at least 45 million kwh annually at a single location): $2400
    3. Other non-residential customers: a rate "established in a manner that avoids abrupt or excessive total net electric bill impacts for typical customers"
    The amounts collected are to be divided between the nuclear and renewable generation funds, with 88.25% going to the nuclear fund and 11.75% going to the renewables fund (R.C. 3706.53).
  3. The OAQDA must adopt rules to implement R.C. 3706.40-3706.65 pursuant to Ohio Revised Code Chapter 119 by January 1, 2020.

2. Renewable Portfolio Standard (RPS) (R.C. 4928.64): HB 6 reduces the 2026 benchmark for the RPS from 12.5% to 8.5%, while eliminating the RPS's "solar carve-out" in 2020. It also cuts off the RPS as of the end of 2026 by eliminating any maintenance of the standard for "every year thereafter." (This will likely harm project developers' ability to obtain long-term financing). Electric distribution utilities may still continue to recover ongoing costs of renewable contracts through December 31, 2032, if they were executed before April 1, 2014, and the costs were being recovered through a bypassable charge as of September 12, 2014 (R.C. 4928.641).

  1. R.C. 4928.642 further reduces the RPS compliance requirement for 2020-2026, reducing the annual compliance obligation for all entities by the amount of kilowatt hours produced by qualifying renewable resources certified under R.C. 3706.40. This reduction is applied proportionally to all electric distribution utilities and electric services companies based on their existing compliance baseline. R.C. 4928.645(C) does provide that the qualifying resources receiving credits from the renewable generation fund under R.C. 3706.45 cannot "double dip" and also receive credits for compliance with the Ohio RPS under R.C. 4928.645.
  2. R.C. 4928.644(B) further reduces the RPS compliance requirement for 2020-2026. It exempts self-assessing purchasers (with annual usage of at least 45 million kwh at a single location) from the compliance baseline calculation under R.C. 4928.643, and also exempts those customers from all RPS charges.

3. Energy Efficiency Resource Standard (EERS) (R.C. 4928.66): HB 6 eliminates the ongoing annual EERS energy savings requirement after 2020, while extending all existing portfolio plans through December 31, 2020 (R.C. 4928.66(A)(1) (a), (F)). After 2020, R.C. 4928.66(G) effectively applies a cumulative savings target of 17.5%. Specifically, by February 1, 2021, the PUCO must determine the cumulative savings achieved by each electric distribution utility under the EERS through December 31, 2020, based on savings banked under R.C. 4928.662(G) compared to the collective usage baseline from 2018-2020. If those savings equal at least 17.5% of the collective baseline, compliance with R.C. 4928.66 is deemed to be achieved.

If collective savings through 2020 are less than 17.5% of the overall baseline, the PUCO must determine how to further implement energy efficiency programs to achieve cumulative energy savings "equal to seventeen and one-half percent, and not more, of the baseline." Once the utilities collectively reach the 17.5% cumulative savings benchmark, any cost recovery for compliance with R.C. 4928.66 "shall terminate." The current utility plans are designed to achieve at least 8.2% cumulative energy savings by the end of 2020, and the four utilities have banked savings ranging from 4-12% of baseline as of the end of 2018 (with the potential to add more banked savings in 2019 and 2020). Accordingly, the utilities are likely to satisfy most or all of the 17.5% cumulative savings requirement by the end of 2020.

  1. Future Voluntary Energy Efficiency Programs?: Note that R.C. 4905.70, which predates R.C. 4928.66, separately requires the PUCO to "initiate programs that will promote and encourage conservation of energy and a reduction in the growth rate of energy consumption, promote economic efficiencies, and take into account long-run incremental costs." That provision has been the source of authority for PUCO approval of natural gas conservation programs and presumably is the basis for statements by at least some electric distribution utilities that they will continue to run efficiency programs even after achieving compliance with R.C. 4928.66. Additionally, R.C. 4928.143(B)(2)(i) authorizes an electric distribution utility to include energy efficiency programs as part of a future Electric Security Plan.
  2. Mercantile Opt-Out: Amended R.C. 4928.6610 expands the energy efficiency opt-out to all mercantile customers as of January 1, 2020, with the opt-out applying any "portfolio plan" implemented under R.C. 4928.66 or under the PUCO's energy efficiency rules as currently codified or "hereafter recodified or amended." (That definition of "portfolio plan" is likely intended to apply the opt-out to future efficiency programs implemented under R.C. 4905.70 or other PUCO authority.) HB 6 also repeals R.C. 4928.6616, removing the requirement for opt-out customers to submit reports to the PUCO regarding their independent efficiency efforts.

4. OVEC: HB 6 creates a definition of "legacy generation resource" encompassing OVEC's Clifty Creek coal plant in Madison, IN (1,303 MW) and Kyger Creek coal plant in Cheshire, OH (1,086 MW) (R.C. 4928.01(A)(41)). The PUCO must create new riders to recover OVEC's "prudently incurred costs" from customers of all four Ohio electric distribution utilities (replacing any existing OVEC riders, which have to date been approved for AEP Ohio, Dayton Power & Light, and Duke Energy Ohio), starting on January 1, 2020 and lasting through December 31, 2030 (R.C. 4928.148). The rate design for the OVEC riders subject to monthly customer caps are as follows (R.C. 4928.148(A)(2)):

  1. Residential customers: $1.50
  2. Other customer classes: comparable monthly caps for each class, not to exceed $1500 per customer

If the costs exceed the monthly caps, they are to be deferred as a regulatory asset that may be recovered as determined by the PUCO. The PUCO must review claimed costs to make a prudence and reasonableness determination in 2021 (for 2020), 2024 (for 2021-2023), 2027 (for 2024-2026), and 2030 (for 2027-2029) (R.C. 4928.148).

5. Other:

  1. Mercantile Renewable Agreements (R.C. 4928.47): On a nondiscriminatory basis and subject to PUCO approval, an electric distribution utility may "enter into an agreement having a term of three years or more with a mercantile customer or group of mercantile customers for the purpose of constructing a customer sited renewable energy resource in this state that will provide the mercantile customer or group with a material portion of the customer's or group's electricity requirements." However, any direct or indirect costs of the renewable resource must be paid for by the utility and the mercantile customer(s), and cannot be collected from any other customers. A mercantile customer is "a commercial or industrial customer if the electricity consumed is for nonresidential use and the customer consumes more than seven hundred thousand kilowatt hours per year or is part of a national account involving multiple facilities in one or more states" (R.C. 4928.01(A)(19)).
  2. Decoupling (R.C. 4928.471): Authorizes electric distribution utilities to file an application for a decoupling mechanism for 2019 and each year thereafter that will decouple "base distribution rates for residential and commercial customers . . . to the base distribution revenue and revenue resulting from implementation of section 4928.66 of the Revised Code excluding program costs and shared savings, and recovered pursuant to an approved electric security plan" for calendar year 2018. The decoupling mechanism is to last until PUCO approval of new base distribution rates for the utility. This provision appears to allow recovery of "lost distribution revenues" in connection with energy efficiency programs as of 2018 regardless of whether a utility continues to implement energy efficiency programs that achieve energy savings in future years, unless the PUCO deems that recovery to constitute "double recovery," which is barred under R.C. 4928.471(C).
  3. PILOT (R.C. 5727.75): HB 6 amends this provision to allow projects with nameplate capacity under 20 MW to qualify for the PILOT without approval by the relevant board of county commissioners under R.C. 5727.75(E)(1) (b) or (c).
  4. Local Jurisdiction Over Wind Farms 20MW and Less (R.C. 4906.13): HB 6 eliminates statewide Ohio Power Siting Board (OPSB) jurisdiction over on-site, customer-generating, behind-the-meter wind projects of 20MW or less. The law allows municipalities and other (local) political subdivisions to regulate such projects. The new law maintains OPSB jurisdiction over projects greater than 20MW, or projects of 5-20MW if not behind-the-meter.

The content of this article is intended to provide a general guide to the subject matter. Specialist advice should be sought about your specific circumstances.

To print this article, all you need is to be registered on Mondaq.com.

Click to Login as an existing user or Register so you can print this article.

Authors
Similar Articles
Relevancy Powered by MondaqAI
 
In association with
Related Topics
 
Similar Articles
Relevancy Powered by MondaqAI
Related Articles
 
Related Video
Up-coming Events Search
Tools
Print
Font Size:
Translation
Channels
Mondaq on Twitter
 
Mondaq Free Registration
Gain access to Mondaq global archive of over 375,000 articles covering 200 countries with a personalised News Alert and automatic login on this device.
Mondaq News Alert (some suggested topics and region)
Select Topics
Registration (please scroll down to set your data preferences)

Mondaq Ltd requires you to register and provide information that personally identifies you, including your content preferences, for three primary purposes (full details of Mondaq’s use of your personal data can be found in our Privacy and Cookies Notice):

  • To allow you to personalize the Mondaq websites you are visiting to show content ("Content") relevant to your interests.
  • To enable features such as password reminder, news alerts, email a colleague, and linking from Mondaq (and its affiliate sites) to your website.
  • To produce demographic feedback for our content providers ("Contributors") who contribute Content for free for your use.

Mondaq hopes that our registered users will support us in maintaining our free to view business model by consenting to our use of your personal data as described below.

Mondaq has a "free to view" business model. Our services are paid for by Contributors in exchange for Mondaq providing them with access to information about who accesses their content. Once personal data is transferred to our Contributors they become a data controller of this personal data. They use it to measure the response that their articles are receiving, as a form of market research. They may also use it to provide Mondaq users with information about their products and services.

Details of each Contributor to which your personal data will be transferred is clearly stated within the Content that you access. For full details of how this Contributor will use your personal data, you should review the Contributor’s own Privacy Notice.

Please indicate your preference below:

Yes, I am happy to support Mondaq in maintaining its free to view business model by agreeing to allow Mondaq to share my personal data with Contributors whose Content I access
No, I do not want Mondaq to share my personal data with Contributors

Also please let us know whether you are happy to receive communications promoting products and services offered by Mondaq:

Yes, I am happy to received promotional communications from Mondaq
No, please do not send me promotional communications from Mondaq
Terms & Conditions

Mondaq.com (the Website) is owned and managed by Mondaq Ltd (Mondaq). Mondaq grants you a non-exclusive, revocable licence to access the Website and associated services, such as the Mondaq News Alerts (Services), subject to and in consideration of your compliance with the following terms and conditions of use (Terms). Your use of the Website and/or Services constitutes your agreement to the Terms. Mondaq may terminate your use of the Website and Services if you are in breach of these Terms or if Mondaq decides to terminate the licence granted hereunder for any reason whatsoever.

Use of www.mondaq.com

To Use Mondaq.com you must be: eighteen (18) years old or over; legally capable of entering into binding contracts; and not in any way prohibited by the applicable law to enter into these Terms in the jurisdiction which you are currently located.

You may use the Website as an unregistered user, however, you are required to register as a user if you wish to read the full text of the Content or to receive the Services.

You may not modify, publish, transmit, transfer or sell, reproduce, create derivative works from, distribute, perform, link, display, or in any way exploit any of the Content, in whole or in part, except as expressly permitted in these Terms or with the prior written consent of Mondaq. You may not use electronic or other means to extract details or information from the Content. Nor shall you extract information about users or Contributors in order to offer them any services or products.

In your use of the Website and/or Services you shall: comply with all applicable laws, regulations, directives and legislations which apply to your Use of the Website and/or Services in whatever country you are physically located including without limitation any and all consumer law, export control laws and regulations; provide to us true, correct and accurate information and promptly inform us in the event that any information that you have provided to us changes or becomes inaccurate; notify Mondaq immediately of any circumstances where you have reason to believe that any Intellectual Property Rights or any other rights of any third party may have been infringed; co-operate with reasonable security or other checks or requests for information made by Mondaq from time to time; and at all times be fully liable for the breach of any of these Terms by a third party using your login details to access the Website and/or Services

however, you shall not: do anything likely to impair, interfere with or damage or cause harm or distress to any persons, or the network; do anything that will infringe any Intellectual Property Rights or other rights of Mondaq or any third party; or use the Website, Services and/or Content otherwise than in accordance with these Terms; use any trade marks or service marks of Mondaq or the Contributors, or do anything which may be seen to take unfair advantage of the reputation and goodwill of Mondaq or the Contributors, or the Website, Services and/or Content.

Mondaq reserves the right, in its sole discretion, to take any action that it deems necessary and appropriate in the event it considers that there is a breach or threatened breach of the Terms.

Mondaq’s Rights and Obligations

Unless otherwise expressly set out to the contrary, nothing in these Terms shall serve to transfer from Mondaq to you, any Intellectual Property Rights owned by and/or licensed to Mondaq and all rights, title and interest in and to such Intellectual Property Rights will remain exclusively with Mondaq and/or its licensors.

Mondaq shall use its reasonable endeavours to make the Website and Services available to you at all times, but we cannot guarantee an uninterrupted and fault free service.

Mondaq reserves the right to make changes to the services and/or the Website or part thereof, from time to time, and we may add, remove, modify and/or vary any elements of features and functionalities of the Website or the services.

Mondaq also reserves the right from time to time to monitor your Use of the Website and/or services.

Disclaimer

The Content is general information only. It is not intended to constitute legal advice or seek to be the complete and comprehensive statement of the law, nor is it intended to address your specific requirements or provide advice on which reliance should be placed. Mondaq and/or its Contributors and other suppliers make no representations about the suitability of the information contained in the Content for any purpose. All Content provided "as is" without warranty of any kind. Mondaq and/or its Contributors and other suppliers hereby exclude and disclaim all representations, warranties or guarantees with regard to the Content, including all implied warranties and conditions of merchantability, fitness for a particular purpose, title and non-infringement. To the maximum extent permitted by law, Mondaq expressly excludes all representations, warranties, obligations, and liabilities arising out of or in connection with all Content. In no event shall Mondaq and/or its respective suppliers be liable for any special, indirect or consequential damages or any damages whatsoever resulting from loss of use, data or profits, whether in an action of contract, negligence or other tortious action, arising out of or in connection with the use of the Content or performance of Mondaq’s Services.

General

Mondaq may alter or amend these Terms by amending them on the Website. By continuing to Use the Services and/or the Website after such amendment, you will be deemed to have accepted any amendment to these Terms.

These Terms shall be governed by and construed in accordance with the laws of England and Wales and you irrevocably submit to the exclusive jurisdiction of the courts of England and Wales to settle any dispute which may arise out of or in connection with these Terms. If you live outside the United Kingdom, English law shall apply only to the extent that English law shall not deprive you of any legal protection accorded in accordance with the law of the place where you are habitually resident ("Local Law"). In the event English law deprives you of any legal protection which is accorded to you under Local Law, then these terms shall be governed by Local Law and any dispute or claim arising out of or in connection with these Terms shall be subject to the non-exclusive jurisdiction of the courts where you are habitually resident.

You may print and keep a copy of these Terms, which form the entire agreement between you and Mondaq and supersede any other communications or advertising in respect of the Service and/or the Website.

No delay in exercising or non-exercise by you and/or Mondaq of any of its rights under or in connection with these Terms shall operate as a waiver or release of each of your or Mondaq’s right. Rather, any such waiver or release must be specifically granted in writing signed by the party granting it.

If any part of these Terms is held unenforceable, that part shall be enforced to the maximum extent permissible so as to give effect to the intent of the parties, and the Terms shall continue in full force and effect.

Mondaq shall not incur any liability to you on account of any loss or damage resulting from any delay or failure to perform all or any part of these Terms if such delay or failure is caused, in whole or in part, by events, occurrences, or causes beyond the control of Mondaq. Such events, occurrences or causes will include, without limitation, acts of God, strikes, lockouts, server and network failure, riots, acts of war, earthquakes, fire and explosions.

By clicking Register you state you have read and agree to our Terms and Conditions